East Pleasant Street and Triangle Street Spring Construction Schedule

pe02679_

 

  East Pleasant Street and Triangle Street

Spring Construction Schedule

Construction for water and sewer lines will begin on East Pleasant Street intersection on March 27th, 2017

Water and sewer work.  March 27th to May 8, 2017 the following work will be underway.

           

  • Water Distribution System improvements through and around the intersection.
  • Sewer Collection System Improvements on East Pleasant Street between Hallock Street and Pray Street.
  • Water Distribution System improvements on Pray Street. 

 

During this phase of work the intersection will be open to vehicle traffic and Police traffic details will be present to control the flow of traffic.

Additional updates will follow on the schedule for construction during the summer.

For questions or additional information concerning this project contact the Amherst Department of Public Works at 413-259-3050 or at publicworks@amherstma.gov

Time of issue: 3/22/2017, 9:00 AM  

 

Issued by:     Jason O. Skeels, P.E., 

                        Town Engineer,

                         Department of Public Works

                         Amherst, MA 