PRESS RELEASE
FISHER, HARRIS, & MT PLEASANT STREETS
CONSTRUCTION
Starting Monday, April 10th, 2017
6:00 am to 4:00 pm
Warner Brothers LLC will start construction work on Fisher
St, Harris St, and Mount Pleasant St next week between 6:00 am and 4:00 pm.
Structure adjustments will begin, followed by reclaiming. Fine grading and
compaction will follow in these areas after the reclaiming has finished.
Monday April 10th: Structures crews
will be removing manhole covers and catch basin tops in preparation for roadway
reclamation.
Tuesday April 11th: All three roads
will be reclaimed and compacted.
Thursday and Friday April 13th and 14th:
Fisher St and Harris St will be fine graded and the excess reclaimed material
will be removed in preparation for the first coat of pavement.
The roads will remain open to through traffic but travelers
are advised to expect minor delays.
All roads will remain open to local traffic.
Please use caution and expect delays around construction equipment.
Please wait for the contractor to smooth out any excess asphalt/gravel piles
before attempting to pass with a vehicle. If you are uncertain whether it is safe
to pass, please communicate your needs/intentions with the contractor, foreman
or Town Inspector on site.
NO ON STREET PARKING
PAY ATTENTION TO DETAIL OFFICERS DIRECTING TRAFFIC
FOLLOW CONSTRUCTION SIGNS
SLOW DOWN IN WORK ZONES
For questions or additional information concerning this
project contact
the Amherst Department of Public Works at 413-259-3050 or at publicworks@amherstma.gov
Issued by: Jason O. Skeels, P.E.,
Town Engineer,
Department of Public Works
Amherst, MA