In the News Home
The original item was published from 6/9/2017 3:07:11 PM to 7/7/2017 5:10:04 PM.

In the News

amherstma.gov - News & Announcements

Posted on: June 9, 2017

[ARCHIVED] E Pleasant St and Triangle St Intersection CONSTRUCTION UPDATE

backhoe_underconstruction

East Pleasant Street and Triangle Street

Intersection Improvements


CONSTRUCTION UPDATE

Eversource Energy has completed removing all overhead electric utility wires in the Triangle and East Pleasant St area.

? Comcast and Verizon will continue making preparations to remove their respective overhead utility wires and the remaining poles.

? Temporary traffic signals have been installed at the intersection of Triangle St and North Pleasant St in preparation for the partial closure of the Triangle and East Pleasant St Intersection.

? Construction materials will continue to be delivered to the north end of Kendrick Park.

? We anticipate Warner Brothers will move in and begin the road work and the intersection closure within the next few weeks, pending the complete removal of all overhead utilities.


NO PARKING ON NORTH PLEASANT ST BETWEEN HALLOCK ST AND TRIANGLE ST


PLEASE SEE ATTACHED SKETCHES FOR PROPOSED CONSTRUCTION DETOUR ROUTES (
Route 1, Route 2, Route 3, Route 4, Route 5)


ADDITIONAL CONSTRUCTION UPDATES AND ACTUAL ROAD CLOSURE NOTICES WILL BE POSTED AS DATES BECOME AVAILABLE.


For questions or additional information concerning this project contact the Amherst Department of Public Works at 413-259-3050 or at publicworks@amherstma.gov

Time of issue: 6/9/2017, 3:00 PM
Issued by: Jason O. Skeels, P.E.,Town Engineer,Department of Public Works Amherst, MA


Facebook Twitter Email

Other News in amherstma.gov - News & Announcements

Image of a street sweeper brush with green bristles, text street sweeping schedule in white.

Street Sweeping Schedule Announced

Posted on: March 22, 2023
 A red fire hydrant with a yellow attachment flushing water out of it.

2023 Scheduled Water Main Flushing

Posted on: April 26, 2023