North Common
Reconstruction
begins
Thursday, September 7th, 2023
Public Works crews will begin removal of the parking machines, benches, planters and picnic tables on the north end of the Town Common on Thursday September 7th, 2023.
Monday, September 11th, 2023
Caracas Construction will begin North Common reconstruction starting with closure of the parking lot in front of Town Hall. The parking lot will be fenced off and used as construction staging area for the duration of the reconstruction project. Both the North Common and the parking lot will be closed to the public during construction.
The project is expected to last through the spring of 2024.
For questions or additional information concerning this project contact the Amherst Department of Public Works at 413-259-3050 or at publicworks@amherstma.gov
Time of issue: 9/5/2023, 8:00 AM
Issued by: Jason O. Skeels, P.E., Town Engineer,
Department of Public Works
Amherst, MA