PAVING UPDATE
for
NORTHAMPTON RD
Early AM Paving
Monday - Thursday
Monday, October 2nd, 1am-6am
Caracas Construction and Warner Bros will be paving the Intersection of South Pleasant St, Northampton Rd and College St at night. Work is expected to be completed by 6 am. All traffic will be detoured during intersection paving.
Tuesday-Wednesday, October 3rd & 4th, 1am-9am
Caracas Construction and Warner Bros will be paving Northampton Rd at night, working their way from South Pleasant St to University Dr. Traffic will be reduced to one lane of traffic in alternating directions as directed by the detail officers.
Thursday, October 4th, 1am-6am
Caracas Construction and Warner Bros will be paving the Intersection of University Dr and Northampton Rd at night. Work is expected to be completed by 6 am. All traffic will be detoured via Amity St/Rocky Hill Rd and North Maple St in Hadley. Snell St will be closed to through traffic.
➢ EXPECT DELAYS & SEEK ALTERNATE ROUTES
➢ PAY ATTENTION TO DETOUR SIGNAGE AND DETAIL OFFICERS
➢ SLOW DOWN IN WORK ZONES
All work is weather dependent.
For questions or additional information concerning this project contact the Amherst Department of Public Works at 413-259-3050 or at publicworks@amherstma.gov
Time of issue: 9/29/2023, 9:00 AM
Issued by: Jason O. Skeels, P.E.,
Town Engineer,
Department of Public Works
Amherst, MA