Posted on: June 20, 2011

[ARCHIVED] Revised Paving Schedule for June 20-25, 2011

Monday, June 20
McClellan Street – Adjust structures to finished grade
Chestnut Street – Lower and plate structures
Amity Street – Install berm
University Drive – Grading, site work, electrical work

Tuesday, June 21
Chestnut Street/North Whitney Street – Lower and plate structures
Amity Street – Install berm
Shutesbury Road – pave driveway aprons
University Drive – pave 1st and 2nd courses of asphalt

Wednesday, June 22
North Whitney/Harvard Ave. – Lower and plate structures
Shays Street – pave driveway aprons
University Drive – Adjust structures

Thursday, June 23
South East Street – Lower and plate structures (Main St. to College St.)
South East Street (South Amherst Common area) – pave driveway aprons
University Drive – Install granite curbing

Friday, June 24
Triangle Street – Lower and plate structures
South East Street (South Amherst Common area) – pave driveway aprons
University Drive – Install granite curbing

This is part of the 4.5 million dollar bond project that was approved in the fall of 2010.
For questions or additional information concerning this project, check the
town website at www.amherstma.gov and follow links to
Departments/Public Works/Projects/Town Wide Resurfacing Project,
contact the DPW office at 259-3050, or email the DPW at
publicworks@amherstma.gov.
Time of issue: 6/20/2011, 9:30 a.m.
Issued by: Engineering Division, Department of Public Works