[ARCHIVED] Paving Schedule as of July 1, 2011

Monday, July 4

INDEPENDENCE DAY!!! CELEBRATE WITH HOT DOGS, HAMBURGERS AND FIREWORKS!!!
Tuesday, July 5

South East Street (Main to College and FSB to Col. Village) – Reclaim
Chestnut Street and South East Street - Grading
Various streets – driveway aprons
University Drive – Install granite curbing, sidewalk construction, site work

Wednesday, July 6
Gaylord St. and South Prospect St. – Reclaim and grade
South East Street – Continue grading
University Drive – Install granite curbing, sidewalk construction, site work

Thursday, July 7
Meadow Street – Reclaim and grade
Gaylord St., South Prospect St. and Meadow St. – Continue grading
Chestnut Street – Place 1st course of asphalt
Various streets – Continue work on driveway aprons
University Drive – Install granite curbing, sidewalk construction, site work

Friday, July 8
Meadow Street – Continue grading
Gaylord St. and South Prospect St. – place 1st course asphalt
Amity Street – Place top coat of asphalt
Various streets – Continue work on driveway aprons
University Drive – Install granite curbing, sidewalk construction, site work

This is part of the 4.5 million dollar bond project that was approved in the fall of 2010.
Please check back for frequent updates.

For questions or additional information concerning this project, check the town website at
www.amherstma.gov and follow links to Departments/Public Works/Projects/Town Wide Resurfacing
Project, contact the DPW office at 259-3050, or email the DPW at publicworks@amherstma.gov.
Time of issue: 6/30/2011, 3:00 p.m.
Issued by: Engineering Division, Department of Public Works